Court resurfacing

The upper courts (1 and 2) will be resurfaced in "Tiger Turf" by Chiltern.

The work is due to start on 27th April  and is expected to last for 3 weeks, weather permitting. The work will potentially finish on Friday 15th May.

Courts 3 and 4 will be available during this time.