Build Week 9 Done. Progress!

Its been good to see the glass on courts 3 and 4 really make them look like the finished article this week.  There is a bit still to do but the main bulk of our efforts now moves on to courts 1 and 2.

Arriving this week will be the steel for both front courts so the fitters can continue their excellent build work and get those frames up next.  After that they'll be glazed with the glass already being on site.

Groundworks within the site have now finished as the final top layer of tarmac has been rolled out.  The team, who have worked tirelessly on this project, will now finish off outside the court site to make us some parking spaces and tidy up.

Our electricians continue their amazing work wiring everything up.  They've done an excellent job of ensuring all the cabling and connecting is finished extremely neatly.

The central, social canopy is all but done.  Our joiner will be back later next week to complete the roof tiling and erect a shed for our electrical cabinet.

Turf fitters for courts 3 and 4 are booked in for next week.  Add to this the expected delivery of our nets then those courts will be completely finished and ready for some trial matches.

Finally, we hope to announce our opening information next week,  it is possible that we may begin with daytime only bookings whilst we finish our electrical work for the floodlights.  All the information will be sent to all those who have subscribed to our mailing list, follow us on social mediia and also be posted here.