Tennis Court Upgrade Work - update: 17 May 2024
Fri, 17 May 2024 00:00
Works update: 17/05/2024
Final Painting work is provisionally scheduled for w/c 27 May 2024 across all three sites (Kidwells Park, Goswells Park/Alexandra Gardens and Desborough Park). The painting and curing of the paint is expected to take around 5 days at each site.
Gate installation is planned for w/c 27 May 2024 at Goswells Park/Alexandra Gardens.
Adjustments are required to the gate at Kidwells Park which we are aiming to complete during the same period as above.
Subject to the above being completed the courts will be open to the public from this time.
Desborough Park courts are avaiable to book from 17/05/2024 - if you notice any errors with the website or the booking process, or wish to provide feedback please contact sports.development@rbwm.gov.uk