Afternoon all (27/7/23),
Further to the last update on the various agreed club " enhancements" please see further update position below;
Agreed Initiative Approx Cost Implementation date Person(s) responsible for delivery
Club Heating - Radiant c£1.23k In progress for Sept deadline Mike T/Martin W
Quote of £2.6k now covered both main clubhouse main room and toilets/changing rooms.
Option selected to do Communal Area first, (excl kitchen) then assess Changing rooms option at a later date.
Door closers to be fitted to both Changing room entrance doors to help retain heat in cooler months.
Club Insulation c£Nil Now not to be implemented (after calcs) Martin W/Mike T
Insulation only effective on convention heat, not radiant heat, so not now necessary.
Solar Lights to Pathways/Courts c£0.5k TBC To be reviewed further in Oct/Nov Mike T/Martin W
Agreed in principle, but to be reviewed further in October (next meeting) in line with finance position check.
CCTV FOC March 2023 - 95% Done - now functional.
1 extra internal camera for Clubhouse may be fitted (TBC at later date) Enclosure for DVR Box (c£70) Mike T/Caroline H email went out 12/6/23 to members .
CCTV/GDPR (Policy renewal/ICO) c£75 Annually Annually - May and June. Mike T - Done for 2023
Window Replacement (Toilets) c£2.35k Done – installed 21st July 2023 Martin W.
Wi-Fi Install c£TBC Annually Annually (If installed) Mike T
Deferred to next meeting.
Soffits/Fascias refurb. c£1.45k TBC July 2023 - Done (finished 18/7/23) Martin W
Court Cleaning c£TBC(major clean) Annually - first in early 2024 John W (plus Gardener G
NB Cleaning Schedule now in place re regular “weekly” clearance activity using brushes/leaf blowers etc via Coaching staff and members – To help mitigate both possible damage to the courts, and any potential slip risk on courts.
Additional Coaching Shed/paving c£1.5K TBC - to reconsider for 2024 Nigel R/Danny B Due to agreement to re-allocation at last Committee meeting of Coaching courts requirement, match practice, and funding priorities, this is now deferred for consideration next year.
Defibrillator c£1.1k Early August 2023 Mike T with
New Defib to be fitted - option put to Committee and all agreed to this option. Judith R for checklist mtce etc Patrick NB. Zoll AED gives 5/7 year warranty - Mike has purchase order and given to Jon W to sort. B helping with printing of manuals
Water Mist Fire Extinguisher c£90 plus £50 Annually - End July for install. Mike T/Patrick B
"Mtce free" = £90 for extinguisher, incl training and site survey and first check certificate (check & regas every 10 years only - Mtce would have been £30/year) All agreed, and Mike has ordered Extinguisher plus Fire Blanket.
Note; JPB to sort out associated training for Fire Extinguisher, plus FRA process etc to assess viability of SLTC doing own FRA (Fire Risk Assessment)
Benches and Scorecards (2 No) c£0.2k Done. June 2023 - Scorecards and benches now on courts 5 & 6 Jon W
NOTE; Total Approx cost of above; c£9k (Excl annual charges) - Tangible Orders totalling c£6k done so far.....
Above subject to a couple of other items as follows;
Strips of Bird deterrent Spikes to top of Floodlights - will need portable "cherry picker" to enable fitment - possible cost TBC - due to height safety issues, preferred option may be to sub contract this out.
Nigel R and Mike T to look at this over the next few weeks.
Paul B has given me some possible companies to take a look at options/costs to improve the car park entrance driveway area – Martin W met chap called Mark Dobson (Paving subbie) on site just before the meeting on 22/7/23 – Quote awaited.
New downpipe to guttering required (existing is totally rotten) Done 25/7/23 – cost of £75. Martin W.
Possible requirement for handrail to steps down to Court 4?....Martin W to obtain quotation for consideration.
Further Additional Items from last meeting;
Wind Break – Needs perimeter fence post integrity checks – Nigel R to find out more and advise at next meeting.
Doors to view courts 3&4 – Maybe option to install 2 “half door/windows” opening onto Courts 3&4 – Caroline H to investigate and advise at next Committee meeting.