As work progresses on the construction of our additional new courts we will add new photos below.
12 May 2024 - how it was
13 May 2024 - work begins
14 May 2024 - working on the edges
16-17 May 2024 - gates removed and begin levelling
19 May 2024 - rolled, compacted and levelled
22-23 May 2024 - laying down the aggregate
30 May 2024 - kerbs going in
4 June 2024 - some of the fencing going up
7-10 June 2024 - fencing going up
12-13 June 2024 - first layer of tarmac going down
2 July 2024 - netting going up, bags of artificial clay delivered
3 August 2024 - carpet going down before articial clay is to be applied.
19 August 2024 - ready for play!!