Day 1 of the court 5 re-surfacing with contractors on site drilling holes into the existiing hard court surface and filling with small stone. This will help drainage of the new court when laid on top of the existing surface.
Edging stones will then be replaced before the new 40mm of tarmac is laid and rolled to 30mm when compacted.
Keep an eye on progress when you visit the club or check out the Club news section over the next couple of weeks.